GPA – Grupo Pão de Açúcar

The project for the Pão de Açúcar Group was carried out with the scope of Global Contract that included all parts of Electrical, Gas, Data, IT, Civil, and Paint, Hydraulic and Fire installations.

Construction Management

HELCO ENGENHARIA faced many challenges at the beginning to manage its projects. As it had a short-term schedule for all, purchases, decision making, activities start-up and new fronts, Helco had to work with tight deadlines, and had to make last minute purchases, not being able to negotiate the price with the suppliers.

Currently, using the SIECON tool, this assists in guaranteeing results, proving easier for organizations to prevent future losses. This tool has made us feel more comfortable acknowledging control on our expectations and working processes.

Client:
GPA – Pão de Açúcar
Total Area:
4.700m²
Complete:
DEC/2017
Deadline:
05 months
Making:
Executed on deadline
Project Local:
Costa Azul, Salvador - BA
Project Segment:
Retail