Walmart Pacaembú

The project for Walmart Pacaembú counted on the services of Reinvention 2017 with Global Contract that included all part of Electrical, Gas, Data, IT, Civil facilities, besides Painting, hydraulics and Fire.

Construction Management

HELCO ENGENHARIA faced many challenges at the beginning to manage its projects. As it had a short-term schedule for all, purchases, decision making, activities start-up and new fronts, Helco had to work with tight deadlines, and had to make last minute purchases, not being able to negotiate the price with the suppliers.

Currently, using the SIECON tool, this assists in guaranteeing results, proving easier for organizations to prevent future losses. This tool has made us feel more comfortable acknowledging control on our expectations and working processes.

Client:
Walmart
Total Area:
15.870m²
Complete:
DEC/2017
Deadline:
95 days
Making:
Executed in 80 days
Project Local:
São Paulo - SP
Project Segment:
Retail